The steps to follow for the installation of finned tube radiators
The finned tube radiator is a kind of heat exchange equipment. The water heater uses a wall-hung boiler or boiler to heat the circulating water, and then connects to the finned tube radiator through pipes, and then outputs the appropriate temperature through the finned tube radiator to form an indoor temperature difference. And then heat cycle, so that the indoor temperature can rise evenly. The installation of the finned tube radiator is an important part, so how should we install it?
1. Before installation, we must carry out on-site measurement to determine the model, number of finned tube radiators and the specific installation location.
2. Various accessories for radiator installation, such as boards, pliers, screwdrivers and other common tools.
3. The pre-installation includes the positioning of heating equipment, slotting, piping, pipe connection, installation of water collector and manifold, pressure test, etc.
4. The later installation includes the installation of the fin tube radiator (including the fixed suspension of the fin tube radiator, the connection of the valve and the fin tube radiator and the heating pipe), the pressure test of the entire system and the installation of the fin tube radiator Debugging etc.
5. Pay attention to the installation and construction process, before or after the construction of water and electricity, it should be carried out before the construction of other decoration procedures.
6. If the heating is installed before decoration, the branch pipe connecting the heating main pipe and the finned tube radiator should be buried under the floor and in the wall. Do not leak the pipe outside to avoid damage.
7. When the finned tube is selected, the number of fins, the width of each fin, the distance between the fins, the way of water intake, and the distance between the interfaces, should be accurate in size to avoid affecting the installation of the fin tube radiator in the later stage.